TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: MAINTENANCE
Post D/T: 10/11/2023 3:19 PM MCT
Notice Eff D/T: 10/11/2023 3:19 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 23-232
Prior Notice: 23-225
Subject: Pocatello to Burley Digs and Oregon City CS ESD Test - Maintenance Schedule Upda
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's website, Northwest will be performing the Oregon City Compressor Station ESD Test on October 19, 2023. The cut point will be the Oregon City Compressor Station which will be limited to 239,000 Dth/d Northbound.
Please note the change in start date/schedule as this work will now be a one-day outage only. Originally, this work was scheduled to begin on October 16, 2023 and last through October 19, 2023 as referenced in All Shipper Notice #23-225.
Northwest will also be performing emergency digs in the Pocatello to Burley corridor from October 13, 2023 through October 20, 2023. Please note, this is a new project added to the maintenance schedule. The cut point will be the Kemmerer Compressor Station which will be limited to 423,000 Dth/d Northbound.
If primary nomination requests through the Oregon City Compressor Station exceeds the available capacity of 239,000 Dth/d Northbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 250,291 Dth/d Northbound. The deficiency period will continue until the work is completed on October 19, 2023.
If primary nomination requests through the Kemmerer Compressor Station exceeds the available capacity of 423,000 Dth/d Northbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 655,000 Dth/d Northbound. The deficiency period will continue until the work is completed on October 20, 2023.
Please reference the Maintenance Schedule tab at www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services Representative or the hotline at 713-215-6301.
|