TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: MAINTENANCE
Post D/T: 10/05/2023 3:41 PM MCT
Notice Eff D/T: 10/05/2023 3:41 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 23-228
Prior Notice: 23-206, 23
Subject: Sumner CS Electric Start System - Maintenance Complete
Notice Text:
Northwest Pipeline would like to inform its customers that the Sumner Compressor Station Electric Start System project posted on Northwest’s website from September 26 through October 7, 2023 and referenced in Notice #23-206 and 23-167 is now complete.
Northwest will begin accepting nominations back to the design capacity of 960,000 Dth/d Southbound through the Sumner Compressor Station effective for the Evening cycle for gas day October 6, 2023.
With the Sumner Compressor Station back at design, the Chehalis Compressor Station, which is currently limited to 518,000 Dth/d Southbound as noted in Notice # 23-206, will now be scheduled at design capacity of 613,444 Dth/d Southbound for the remainder of the project effective for the Evening cycle for gas day October 6, 2023.
Please reference the Maintenance Schedule tab at www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services Representative or the hotline at 713-215-6301.
|