TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 10/25/2022 9:03 AM MCT
Notice Eff D/T: 10/25/2022 9:03 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 22-173
Prior Notice:
Subject: Burley Maintenance Extended
Notice Text:
As communicated in the maintenance call, Northwest informed customers of a controls upgrade at the Burley compressor. Due to commissioning delays, the maintenance has not been fully completed and Northwest is working diligently to complete this project as soon as possible.
During this time, Northwest will be limiting northbound flows at the Burley compressor to 464,000 Dth/d.
If the primary scheduled quantities for gas day October 26 exceed the operationally available capacity of 464,000 Dth/d at Burley or what Northwest is unable to mitigate, Northwest will give notice of a Deficiency Period based on the northbound design capacity of 579,000 Dth/d. If you have any questions, please call your Commercial Services Representative or the hotline at 713-215-6301.
|