The Northwest Pipeline EBB is best viewed in Internet Explorer 10 or newer, Google Chrome, or Mozilla Firefox.

Northwest Pipeline LLC Notice Detail

Northwest Pipeline LLC


NOTICE # 25-163
Caldwell Compressor Station Deficiency Period posted on Sep 22 2025 4:02PM

TSP Name:  Northwest Pipeline LLC     TSP:  67977322

Critical:  Y
Notice Stat Desc:  SUPERSEDE
Notice Type Desc:  CURTAILMENT
Post D/T:  09/22/2025 4:01 PM MCT
Notice Eff D/T:  09/22/2025 4:01 PM MCT
Notice End D/T:  
Reqrd Rsp Desc:  No response required
Rsp D/T:  

Notice ID:  25-163
Prior Notice:  25-162
Subject:  Caldwell Compressor Station Deficiency Period

Notice Text:

 

As indicated in All Shippers Notice #25-162, Northwest is

currently performing DOT Hydro Tests though the Caldwell

compressor station September 23, 2025 through October 27, 2025.

 

Primary southbound nomination requests at the Caldwell CS have

exceeded the available capacity of 358,000 Dth/d southbound (or

whatever Northwest cannot mitigate). Therefore, pursuant to

Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's

Tariff, Northwest hereby gives notice of a Deficiency Period

for Gas Day September 23, 2025. The Deficiency will be

calculated based on a design capacity of 475,000 Dth/d

southbound. The Deficiency Period will continue until the work

is completed. Northwest will post on its EBB if unable to

mitigate volumes each day until the work is completed.

 

Please reference the Maintenance Schedule tab at

www.northwest.williams.com for more information.

 

 

If you have any questions, please call your Commercial Services

Representative or the hotline at 713-215-6301.