Northwest Pipeline LLC Notice Detail

Northwest Pipeline LLC


NOTICE # 25-115
Schedule Change for Sumas ESD and Mt. Vernon ESD posted on Aug 11 2025 9:14AM

TSP Name:  Northwest Pipeline LLC     TSP:  67977322

Critical:  Y
Notice Stat Desc:  INITIATE
Notice Type Desc:  MAINTENANCE
Post D/T:  08/11/2025 9:13 AM MCT
Notice Eff D/T:  08/11/2025 9:13 AM MCT
Notice End D/T:  
Reqrd Rsp Desc:  No response required
Rsp D/T:  

Notice ID:  25-115
Prior Notice:  
Subject:  Schedule Change for Sumas ESD and Mt. Vernon ESD

Notice Text:

Northwest has the flexibility to take advantage of the 
decreased upstream flows due to upstream maintenance and will 
be swapping the scheduled outages for the Sumas D Plant ESD and 
the Mt. Vernon ESD in an effort to minimize customer impacts. 

- The Sumas D Plant ESD will now be scheduled to begin gas 
        day August 12, 2025, through gas day August 13, 2025. 

- The Mt. Vernon ESD will now be scheduled to begin gas day 
        August 20, 2025, through gas day August 21, 2025.

The Sumas CS will be limited to 1,010,000 Dth/d southbound for 
the duration of the outage.

If primary nomination requests through the Sumas CS exceeds the 
available capacity of 1,010,000 Dth/d southbound (or whatever 
NWP cannot mitigate during any day of the maintenance), 
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in 
Northwest's Tariff, Northwest will give notice of a Declared 
Deficiency Period based on a design capacity of 1,409,000 Dth/d 
southbound. The deficiency period will continue until the work 
has been completed.

Please reference the Maintenance Schedule tab at 
www.northwest.williams.com for more information.

If you have any questions, please call your Commercial Services 
Representative or the hotline at 713-215-6301.