Northwest Pipeline LLC Notice Detail
Northwest Pipeline LLC
NOTICE # 25-112
Chehalis Unplanned Maintenance, Notice of Recall and OFO, and Potential Deficien
posted on
Aug 4 2025 8:30AM
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 08/04/2025 8:28 AM MCT
Notice Eff D/T: 08/04/2025 8:28 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 25-112
Prior Notice:
Subject: Chehalis Unplanned Maintenance, Notice of Recall and OFO, and Potential Deficien
Notice Text:
Northwest is experiencing additional unplanned maintenance at the Chehalis compressor station.
Effective Gas Day Tuesday, August 05, 2025, and until further notice, Northwest is issuing an OFO Recall Advisory and Operational Flow Order (OFO) southbound through the Chehalis compressor pursuant to Section 14.15(d) of its Tariff to bring the station down to design of 672,000 Dth/d southbound. Additionally, the available capacity will be 600,000 Dth/d southbound.
Under the OFO Recall Advisory, Shippers are required to: (1) recall capacity that is subject to an OFO recall provision; or (2) take other action that is acceptable to Northwest, to satisfy its OFO obligation.
If the southbound scheduled quantities exceed Northwest’s design capacity of 672,000 Dth/d at Chehalis Northwest will provide Shippers with their specific OFO obligations by 4:00 p.m. MST. Shippers must comply with their OFO obligations no later than the Evening nomination deadline (5:00 p.m. MST).
If an OFO is necessary for a given Gas Day, Northwest will wait until the Evening scheduling process to provide notice of a Declared Deficiency period and will make deficiency cuts to bring the nomination requests at the Chehalis compressor from the design capacity of 672,000 Dth/d to the operationally available capacity of 600,000 Dth/d. If an OFO is not necessary, but a deficiency period is, Northwest will provide notice of a Declared Deficiency period and will make deficiency cuts in the Timely scheduling process to bring the nomination requests at the Chehalis compressor to the operationally available capacity of 600,000 Dth/d (or whatever NWP cannot mitigate during any day of the unplanned maintenance period), all pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff. The deficiency period will continue until the work is completed.
Northwest Pipeline will work diligently to bring this station back into service as quickly as possible to minimize any impacts.
Shippers can monitor throughput quantities and obtain a copy of Northwest’s OFO procedures on Northwest’s website at www.northwest.williams.com.
If you have any questions, please contact your Commercial Services Representative or the hotline at 713-215-6301.
|
|