NOTICE # 25-089
Boise Loop Line Blowdown - Maintenance Reminder posted on Jun 26 2025 12:02PM

TSP Name:  Northwest Pipeline LLC     TSP:  67977322

Critical:  Y
Notice Stat Desc:  INITIATE
Notice Type Desc:  MAINTENANCE
Post D/T:  06/26/2025 11:59 AM MCT
Notice Eff D/T:  06/26/2025 11:59 AM MCT
Notice End D/T:  
Reqrd Rsp Desc:  No response required
Rsp D/T:  

Notice ID:  25-089
Prior Notice:  
Subject:  Boise Loop Line Blowdown - Maintenance Reminder

Notice Text:

As posted in the maintenance schedule on Northwest Pipeline's 
website, Northwest is performing maintenance at the following 
locations:

   - Buhl CS beginning gas day June 30, 2025, through gas 
        day July 03, 2025.
   - Meacham CS beginning gas day June 30, 2025, through 
        gas day July 03, 2025.

The Buhl CS will be limited to 413,000 Dth/d northbound for the 
duration of the outage.

If primary nomination requests through the Buhl CS exceeds the 
available capacity of 413,000 Dth/d northbound (or whatever NWP 
cannot mitigate during any day of the maintenance), pursuant to 
Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's 
Tariff, Northwest will give notice of a Declared Deficiency 
Period based on a design capacity of 578,000 Dth/d northbound. 
The deficiency period will continue until the work is completed 
on gas day July 03, 2025. 

The Meacham CS will be limited to 461,000 Dth/d southbound for 
the duration of the outage. 

If primary nomination requests through the Meacham CS exceeds 
the available capacity of 461,000 Dth/d southbound (or whatever 
NWP cannot mitigate during any day of the maintenance), 
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in 
Northwest's Tariff, Northwest will give notice of a Declared 
Deficiency Period based on a design capacity of 500,000 Dth/d 
southbound. The deficiency period will continue until the work 
is completed on gas day July 03, 2025. 

Please reference the Maintenance Schedule tab at 
www.northwest.williams.com for more information.

If you have any questions, please call your Commercial Services 
Representative or the hotline at 713-215-6301.