TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 05/29/2025 10:26 AM MCT
Notice Eff D/T: 05/29/2025 10:26 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 25-076
Prior Notice:
Subject: Kemmerer ESD & Caldwell ESD - Maintenance Reminder
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's website, Northwest is performing maintenance at the following locations:
- Kemmerer CS on gas day June 02, 2025. - Caldwell CS beginning gas day June 03, 2025, through gas day June 05, 2025.
The Kemmerer CS will be limited to 729,000 Dth/d northbound for the duration of the outage.
If primary nomination requests through the Kemmerer CS exceeds the available capacity of 729,000 Dth/d northbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 772,925 Dth/d northbound. The deficiency period will continue until the work is completed on gas day June 02, 2025.
The Caldwell CS will be limited to 404,000 Dth/d northbound and 438,000 Dth/d southbound for the duration of the outage.
If primary nomination requests through the Caldwell CS exceeds the available capacity of 404,000 Dth/d northbound or 438,000 Dth/d southbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 452,000 Dth/d northbound or 475,000 Dth/d southbound. The deficiency period will continue until the work is completed on gas day June 05, 2025.
Please reference the Maintenance Schedule tab at www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services Representative or the hotline at 713-215-6301.
|