TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 04/21/2025 10:21 AM MCT
Notice Eff D/T: 04/21/2025 10:21 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 25-053
Prior Notice:
Subject: Sumas A Plant Disconnect & Mt. Vernon Unit 3 Solar Inspections - Maintenance Rem
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's website, Northwest is performing maintenance at the following locations:
- Sumas CS beginning gas day April 23, 2025, through gas day April 25, 2025.
- Mt. Vernon CS on gas day April 23, 2025.
The Sumas CS will be limited to 922,000 Dth/d southbound for the duration of the outage.
If primary nomination requests through the Sumas CS exceeds the available capacity of 922,000 Dth/d southbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 1,409,000 Dth/d southbound. The deficiency period will continue until the work is completed on gas day April 25, 2025.
The Mt. Vernon CS will be limited to 1,241,000 Dth/d southbound for the duration of the outage.
If primary nomination requests through the Mt. Vernon CS exceeds the available capacity of 1,241,000 Dth/d southbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 1,277,000 Dth/d southbound. The deficiency period will continue until the work is completed on gas day April 23, 2025.
Please reference the Maintenance Schedule tab at www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services Representative or the hotline at 713-215-6301.
|