TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 04/18/2025 9:20 AM MCT
Notice Eff D/T: 04/18/2025 9:20 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 25-052
Prior Notice:
Subject: Sumas B Plant Disconnect, Boise CS Generator Install/ESD, Mt. Vernon CS Solar In
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's website, Northwest is performing maintenance at the following locations:
- Sumas CS beginning gas day April 21, 2025, through gas day April 22, 2025.
- Boise CS beginning gas day April 21, 2025, through gas day May 02, 2025.
- Mt. Vernon CS on gas day April 22, 2025.
- Pegram CS beginning on gas day April 22, 2025, through gas day April 23, 2025.
- Pocatello CS beginning gas day April 22, 2025, through gas day April 23, 2025.
The Sumas CS will be limited to 1,069,000 Dth/d southbound for the duration of the outage.
If primary nomination requests through the Sumas CS exceeds the available capacity of 1,069,000 Dth/d southbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 1,409,000 Dth/d southbound. The deficiency period will continue until the work is completed on gas day April 22, 2025.
The Boise CS will be limited to 437,000 Dth/d northbound and 438,000 Dth/d southbound for the duration of the outage.
If primary nomination requests through the Boise CS exceeds the available capacity of 437,000 Dth/d northbound or 438,000 Dth/d southbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 499,000 Dth/d northbound or 452,000 Dth/d southbound. The deficiency period will continue until the work is completed on gas day May 02, 2025.
The Mt. Vernon CS will be limited to 1,177,000 Dth/d southbound for the duration of the outage.
If primary nomination requests through the Mt. Vernon CS exceeds the available capacity of 1,177,000 Dth/d southbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 1,277,000 Dth/d southbound. The deficiency period will continue until the work is completed on gas day April 22, 2025.
The Pegram CS will be limited to 602,000 Dth/d northbound for the duration of the outage.
If primary nomination requests through the Pegram CS exceeds the available capacity of 602,000 Dth/d northbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 654,000 Dth/d northbound. The deficiency period will continue until the work is completed on gas day April 23, 2025.
The Pocatello CS will be limited to 499,000 Dth/d northbound for the duration of the outage.
If primary nomination requests through the Pocatello CS exceeds the available capacity of 499,000 Dth/d northbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 610,000 Dth/d northbound. The deficiency period will continue until the work is completed on gas day April 23, 2025
Please reference the Maintenance Schedule tab at www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services Representative or the hotline at 713-215-6301.
|