Northwest Pipeline LLC Notice Detail

Northwest Pipeline LLC


NOTICE # 24-096
Zillah Engine Exchange & Burley ESD Test - Maintenance Reminder posted on Jun 13 2024 2:44PM

TSP Name:  Northwest Pipeline LLC     TSP:  67977322

Critical:  Y
Notice Stat Desc:  INITIATE
Notice Type Desc:  MAINTENANCE
Post D/T:  06/13/2024 2:42 PM MCT
Notice Eff D/T:  06/13/2024 2:42 PM MCT
Notice End D/T:  
Reqrd Rsp Desc:  No response required
Rsp D/T:  

Notice ID:  24-096
Prior Notice:  
Subject:  Zillah Engine Exchange & Burley ESD Test - Maintenance Reminder

Notice Text:

As posted in the maintenance schedule on Northwest Pipeline's 
website, Northwest is performing work at the Zillah CS 
beginning Gas Day June 17, 2024 through Gas Day June 27, 2024 
and at the Burley CS beginning Gas Day June 18, 2024 through 
Gas Day June 19, 2024. 

The cut point for the Zillah CS Engine Exchange will be the 
Zillah CS which will be limited to 29,000 Dth/d northbound for 
the duration of the project.

The cut point for the Burley CS ESD Test will be the Burley CS 
which will be limited to 464,000 Dth/d northbound for the 
duration of the project. 

If primary nomination requests through the Zillah CS exceed the 
available capacity of 29,000 Dth/d northbound (or whatever NWP 
cannot mitigate during any day of the maintenance), pursuant to 
Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's 
Tariff, Northwest will give notice of a Declared Deficiency 
Period based on a design capacity of 49,114 Dth/d northbound. 
The deficiency period will continue until the work is completed 
on Gas Day June 27, 2024. 

If primary nomination requests through the Burley CS exceed the 
available capacity of 464,000 Dth/d northbound (or whatever NWP 
cannot mitigate during any day of the maintenance), pursuant to 
Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's 
Tariff, Northwest will give notice of a Declared Deficiency 
Period based on a design capacity of 579,000 Dth/d northbound. 
The deficiency period will continue until the work is completed 
on Gas Day June 19, 2024. 


Please reference the Maintenance Schedule tab at 
www.northwest.williams.com for more information.


If you have any questions, please call your Commercial Services 
Representative or the hotline at 713-215-6301.