Northwest Pipeline LLC Notice Detail

Northwest Pipeline LLC


NOTICE # 25-065
Maintenance Reminder - McMinnville Vent Valve, Vernal ESD & Solar Inspection, Bu posted on May 9 2025 8:55AM

TSP Name:  Northwest Pipeline LLC     TSP:  67977322

Critical:  Y
Notice Stat Desc:  INITIATE
Notice Type Desc:  MAINTENANCE
Post D/T:  05/09/2025 7:56 AM MCT
Notice Eff D/T:  05/09/2025 7:56 AM MCT
Notice End D/T:  
Reqrd Rsp Desc:  No response required
Rsp D/T:  

Notice ID:  25-065
Prior Notice:  
Subject:  Maintenance Reminder - McMinnville Vent Valve, Vernal ESD & Solar Inspection, Buhl ESD, Mt. Vernon ESD

Notice Text:

As posted in the maintenance schedule on Northwest Pipeline's 
website, Northwest is performing maintenance at the following 
locations:

- McMinnville CS beginning gas day May 12, 2025, through 
        gas day May 16, 2025.

- Vernal CS beginning gas day May 12, 2025, through gas 
        day May 16, 2025.

- Buhl CS beginning gas day May 13, 2025, through gas 
        day May 14, 2025.

- Mt. Vernon CS beginning gas day May 13, 2025, through gas 
        day May 14, 2025.

- Willard CS beginning gas day May 14, 2025, through gas 
        day May 16, 2025.

The McMinnville CS will be limited to 157,000 Dth/d northbound 
for the duration of the outage. 

If primary nomination requests through the McMinnville CS 
exceeds the available capacity of 157,000 Dth/d northbound (or 
whatever NWP cannot mitigate during any day of the 
maintenance), pursuant to Sections 10.2 and 10.3 of Rate 
Schedule TF-1 in Northwest's Tariff, Northwest will give notice 
of a Declared Deficiency Period based on a design capacity of 
207,000 Dth/d northbound. The deficiency period will continue 
until the work is completed on gas day May 16, 2025. 

The Vernal CS will be limited to 271,000 Dth/d northbound 
and 291,000 Dth/d southbound for the duration of the outage. 

If primary nomination requests through the Vernal CS exceeds 
the available capacity of 271,000 Dth/d northbound or 291,000 
Dth/d southbound (or whatever NWP cannot mitigate during any 
day of the maintenance), pursuant to Sections 10.2 and 10.3 of 
Rate Schedule TF-1 in Northwest's Tariff, Northwest will give 
notice of a Declared Deficiency Period based on a design 
capacity of 353,000 Dth/d northbound or 324,000 Dth/d 
southbound. The deficiency period will continue until the work 
is completed on gas day May 16, 2025. 

The Buhl CS will be limited to 506,000 Dth/d northbound for the 
duration of the outage. 

If primary nomination requests through the Buhl CS exceeds the 
available capacity of 506,000 Dth/d northbound (or whatever NWP 
cannot mitigate during any day of the maintenance), pursuant to 
Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's 
Tariff, Northwest will give notice of a Declared Deficiency 
Period based on a design capacity of 578,000 Dth/d northbound. 
The deficiency period will continue until the work is completed 
on gas day May 14, 2025. 

The Mt. Vernon CS will be limited to 1,177,000 Dth/d southbound 
for the duration of the outage. 

If primary nomination requests through the Mt. Vernon CS 
exceeds the available capacity of 1,177,000 Dth/d southbound 
(or whatever NWP cannot mitigate during any day of the 
maintenance), pursuant to Sections 10.2 and 10.3 of Rate 
Schedule TF-1 in Northwest's Tariff, Northwest will give notice 
of a Declared Deficiency Period based on a design capacity of 
1,277,000 Dth/d southbound. The deficiency period will continue 
until the work is completed on gas day May 14, 2025. 

The Willard CS will be limited to 481,000 Dth/d northbound for 
the duration of the outage. 

If primary nomination requests through the Willard CS exceeds 
the available capacity of 481,000 Dth/d northbound (or whatever 
NWP cannot mitigate during any day of the maintenance), 
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in 
Northwest's Tariff, Northwest will give notice of a Declared 
Deficiency Period based on a design capacity of 540,000 Dth/d 
northbound. The deficiency period will continue until the work 
is completed on gas day May 16, 2025. 

Please reference the Maintenance Schedule tab at 
www.northwest.williams.com for more information.

If you have any questions, please call your Commercial Services 
Representative or the hotline at 713-215-6301.