TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 10/29/2024 8:03 AM MCT
Notice Eff D/T: 10/29/2024 8:03 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 24-188
Prior Notice:
Subject: Goldendale Unit 2 Repairs - Maintenance Reminder
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's website, Northwest is performing repairs to Unit #2 at the Goldendale CS beginning Gas Day October 30, 2024, through Gas Day October 31, 2024. The cut point will be the Goldendale CS which will be limited to 375,000 Dth/d northbound and 375,000 Dth/d southbound for the duration of the outage.
If primary nomination requests through the Goldendale CS exceed the available capacity of 375,000 Dth/d northbound or 375,000 Dth/d southbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 543,000 Dth/d northbound or 393,000 Dth/d southbound. The deficiency period will continue until the work is completed on Gas Day October 31, 2024.
Please reference the Maintenance Schedule tab at www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services Representative or the hotline at 713-215-6301.
|