TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 07/25/2024 2:53 PM MCT
Notice Eff D/T: 07/25/2024 2:53 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 24-114
Prior Notice:
Subject: Chehalis CS Unplanned Maintenance & Albany CS ESD Test and Solar Inspections Mai
Notice Text:
Northwest has added a new unplanned maintenance project to the maintenance schedule on Northwest Pipeline’s website. Northwest is performing work on Unit 1 at the Chehalis CS beginning Gas Day July 29, 2024, through Gas Day July 31, 2024. The available southbound capacity at the Chehalis CS will be limited to the design capacity of 672,000 Dth/d southbound.
Northwest Pipeline will work diligently to bring this station back into service as quickly as possible to minimize any impacts.
As a reminder and as posted in the maintenance schedule on Northwest Pipeline's website, Northwest is performing an ESD Test and Solar Inspections at the Albany CS beginning Gas Day July 30, 2024, through Gas Day July 31, 2024. The cut point will be the Albany CS which will be limited to 116,000 Dth/d southbound for the duration of the outage.
If primary nomination requests through the Albany CS exceed the available capacity of 116,000 Dth/d southbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 120,000 Dth/d southbound. The deficiency period will continue until the work is completed on Gas Day July 31, 2024.
Please reference the Maintenance Schedule tab at www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services Representative or the hotline at 713-215-6301.
|