TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 06/20/2024 9:02 AM MCT
Notice Eff D/T: 06/20/2024 9:02 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 24-099
Prior Notice:
Subject: Meacham M&ERP and Pleasant View M&ERP - Maintenance Reminder
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's website, Northwest is performing M&ERP work at the Meacham CS and at the Pleasant View CS beginning Gas Day June 24, 2024, through Gas Day October 15, 2024.
The cut point for the Meacham M&ERP work will be the Meacham CS which will be limited to 415,000 Dth/d northbound and 469,000 southbound for the duration of the project. (Please note, the lowest available southbound capacity at the Meacham CS posted on Northwest Pipeline’s website will take scheduling priority when maintenance outages overlap.)
The cut point for the Pleasant View M&ERP work will be the Pleasant View CS which will be limited to 259,000 Dth/d northbound and 277,000 Dth/d southbound for the duration of the project.
If primary nomination requests through the Meacham CS exceed the available capacity of 415,000 Dth/d northbound or 469,000 Dth/d southbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 445,000 Dth/d northbound or 500,000 Dth/d southbound. The deficiency period will continue until the work is completed on Gas Day October 15, 2024.
If primary nomination requests through the Pleasant View CS exceed the available capacity of 259,000 Dth/d northbound or 277,000 Dth/d southbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 281,000 Dth/d northbound or 351,000 Dth/d southbound. The deficiency period will continue until the work is completed on Gas Day October 15, 2024.
Please reference the Maintenance Schedule tab at www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services Representative or the hotline at 713-215-6301.
|