Northwest Pipeline LLC Notice Detail

Northwest Pipeline LLC


NOTICE # 24-097
Baker to Meacham SCDDA Digs - Maintenance Update posted on Jun 14 2024 1:08PM

TSP Name:  Northwest Pipeline LLC     TSP:  67977322

Critical:  Y
Notice Stat Desc:  INITIATE
Notice Type Desc:  MAINTENANCE
Post D/T:  06/14/2024 1:07 PM MCT
Notice Eff D/T:  06/14/2024 1:07 PM MCT
Notice End D/T:  
Reqrd Rsp Desc:  No response required
Rsp D/T:  

Notice ID:  24-097
Prior Notice:  
Subject:  Baker to Meacham SCDDA Digs - Maintenance Update

Notice Text:

As posted in the maintenance schedule on Northwest Pipeline’s 
website, Northwest has been performing SCCDA Digs between the 
Baker to Meacham corridor since Gas Day June 05, 2024. To 
continue to safely excavate the line due to current pipeline 
conditions, the southbound flow will have to be restricted 
through the Meacham CS to 460,000 Dth/d southbound effective 
Gas Day June 17, 2024 through Gas Day August 16, 2024. 

If primary nomination requests through the Meacham CS exceed 
the available capacity of 460,000 Dth/d southbound (or whatever 
NWP cannot mitigate during any day of the maintenance), 
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in 
Northwest's Tariff, Northwest will give notice of a Declared 
Deficiency Period based on a design capacity of 500,000 Dth/d 
southbound. The deficiency period will continue until the work 
is completed on Gas Day August 16, 2024. 

Please reference the Maintenance Schedule tab at 
www.northwest.williams.com for more information.


If you have any questions, please call your Commercial Services 
Representative or the hotline at 713-215-6301.