TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 05/31/2024 9:37 AM MCT
Notice Eff D/T: 05/31/2024 9:37 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 24-091
Prior Notice:
Subject: Baker CS ESD Test - Maintenance Reminder
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's website, Northwest is performing work at the Baker CS beginning Gas Day June 04, 2024 through Gas Day June 06, 2024. The cut point will be the Baker CS and the available capacity will be limited to 357,000 Dth/d Northbound and 463,000 Dth/d Southbound.
If primary nomination requests through the Baker CS exceeds the available capacity of 357,000 Dth/d Northbound or 463,000 Dth/d Southbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 446,000 Dth/d Northbound or 491,000 Dth/d Southbound. The deficiency period will continue until the work is completed on Gas Day June 06, 2024.
Please reference the Maintenance Schedule tab at www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services Representative or the hotline at 713-215-6301.
|