Northwest Pipeline LLC Notice Detail

Northwest Pipeline LLC


NOTICE # 24-091
Baker CS ESD Test - Maintenance Reminder posted on May 31 2024 9:39AM

TSP Name:  Northwest Pipeline LLC     TSP:  67977322

Critical:  Y
Notice Stat Desc:  INITIATE
Notice Type Desc:  MAINTENANCE
Post D/T:  05/31/2024 9:37 AM MCT
Notice Eff D/T:  05/31/2024 9:37 AM MCT
Notice End D/T:  
Reqrd Rsp Desc:  No response required
Rsp D/T:  

Notice ID:  24-091
Prior Notice:  
Subject:  Baker CS ESD Test - Maintenance Reminder

Notice Text:

As posted in the maintenance schedule on Northwest Pipeline's 
website, Northwest is performing work at the Baker CS beginning 
Gas Day June 04, 2024 through Gas Day June 06, 2024. The cut 
point will be the Baker CS and the available capacity will be 
limited to 357,000 Dth/d Northbound and 463,000 Dth/d 
Southbound.

If primary nomination requests through the Baker CS exceeds the 
available capacity of 357,000 Dth/d Northbound or 463,000 Dth/d 
Southbound (or whatever NWP cannot mitigate during any day of 
the maintenance), pursuant to Sections 10.2 and 10.3 of Rate 
Schedule TF-1 in Northwest's Tariff, Northwest will give notice 
of a Declared Deficiency Period based on a design capacity of 
446,000 Dth/d Northbound or 491,000 Dth/d Southbound. The 
deficiency period will continue until the work is completed on 
Gas Day June 06, 2024. 


Please reference the Maintenance Schedule tab at 
www.northwest.williams.com for more information.


If you have any questions, please call your Commercial Services 
Representative or the hotline at 713-215-6301.