TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 05/23/2024 9:31 AM MCT
Notice Eff D/T: 05/23/2024 9:31 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 24-083
Prior Notice:
Subject: Rangely Solar Inspections - Maintenance Reminder
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's website, Northwest is performing work at the Rangely CS beginning Gas Day May 28, 2024 through Gas Day May 29, 2024. The cut point will be the Rangely CS which will be limited to 261,000 Dth/d northbound.
If primary nomination requests through the Rangely CS exceed the available capacity of 261,000 Dth/d northbound (or whatever NWP cannot mitigate during any day of the maintenance), pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest will give notice of a Declared Deficiency Period based on a design capacity of 350,000 Dth/d northbound. The deficiency period will continue until the work is completed on May 29, 2024.
Please reference the Maintenance Schedule tab at www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services Representative or the hotline at 713-215-6301.
|