Northwest Pipeline LLC Notice Detail

Northwest Pipeline LLC


NOTICE # 24-062
Buhl CS New Maintenance and Chehalis CS PLC 5 Upgrade Maintenance Reminder posted on Apr 4 2024 3:54PM

TSP Name:  Northwest Pipeline LLC     TSP:  67977322

Critical:  Y
Notice Stat Desc:  INITIATE
Notice Type Desc:  MAINTENANCE
Post D/T:  04/04/2024 3:49 PM MCT
Notice Eff D/T:  04/04/2024 3:49 PM MCT
Notice End D/T:  
Reqrd Rsp Desc:  No response required
Rsp D/T:  

Notice ID:  24-062
Prior Notice:  
Subject:  Buhl CS New Maintenance and Chehalis CS PLC 5 Upgrade Maintenance Reminder

Notice Text:

Northwest has added a new unplanned maintenance project to the 
maintenance schedule on Northwest Pipeline’s website. Northwest 
is performing Solar Inspections at the Buhl Compressor Station 
beginning on Gas Day April 8, 2024 through Gas Day April 12, 
2024. The available Northbound capacity at the Buhl Compressor 
Station will be limited to 506,000 Dth/d Northbound. Please 
note, Northwest does not anticipate any impacts to customers 
during this outage window. 

However, if primary nomination requests through the Buhl 
Compressor Station exceed the available capacity of 506,000 
Dth/d Northbound (or whatever NWP cannot mitigate during any 
day of the maintenance), pursuant to Sections 10.2 and 10.3 of 
Rate Schedule TF-1 in Northwest's Tariff, Northwest will give 
notice of a Declared Deficiency Period based on a design 
capacity of 578,000 Dth/d Northbound. The deficiency period 
will continue until the work is completed on Gas Day April 12, 
2024. 

Furthermore, as posted in the maintenance schedule on Northwest 
Pipeline's website, Northwest is performing a PLC 5 Upgrade at 
the Chehalis Compressor Station beginning on Gas Day April 9, 
2024 through GD April 23, 2024. The cut point will be the 
Chehalis Compressor Station which will be limited to 296,000 
Dth/d Northbound and 490,000 Dth/d Southbound.

If primary nomination requests through the Chehalis Compressor 
Station exceed the available capacity of 296,000 Dth/d 
Northbound or 490,000 Dth/d Southbound (or whatever NWP cannot 
mitigate during any day of the maintenance), pursuant to 
Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's 
Tariff, Northwest will give notice of a Declared Deficiency 
Period based on a design capacity of 759,000 Dth/d Northbound 
or 672,000 Dth/d Southbound. The deficiency period will 
continue until the work is completed on Gas Day April 23, 2024. 

Please reference the Maintenance Schedule tab at 
www.northwest.williams.com for more information.


If you have any questions, please call your Commercial Services 
Representative or the hotline at 713-215-6301.