TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: MAINTENANCE
Post D/T: 08/21/2023 9:33 AM MCT
Notice Eff D/T: 08/21/2023 9:33 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 23-166
Prior Notice: 23-162
Subject: Snohomish Maintenance - Update
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest is performing work at the Snohomish CS from
August 21, 2023 through September 15, 2023. The cut point will
be the Snohomish CS which will be limited to 853,000 Dth/d
southbound.
The outage dates have changed. The construction crews are
currently on site and getting the facility ready for the
outage. Northwest will schedule all noms up to the design
capacity of 1,118,000 Dth/d through gas day August 27, 2023.
Beginning August 28, 2023 the capacity will be limited to
853,000 Dth/d. If primary nomination requests through the
Snohomish CS exceed the available capacity of 853,000 Dth/d
southbound (or whatever NWP can mitigate during any day of the
maintenance), pursuant to Sections 10.2 and 10.3 of Rate
Schedule TF-1 in Northwest's Tariff, Northwest will give notice
of a Declared Deficiency Period based on a design capacity of
1,118,000 Dth/d southbound. The deficiency period will continue
until the work is completed on September 15, 2023.
Please reference the Maintenance Schedule tab at
www.northwest.williams.comfor more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.