Northwest Pipeline LLC NOTICE #32979 Burley Compressor Station Deficiency Period posted on Aug 19 2026 3:27PM TSP Name: Northwest Pipeline LLC TSP: 67977322 Critical: Y Notice Stat Desc: SUPERSEDE Notice Type Desc: CURTAILMENT Post D/T: 08/19/2026 3:25 PM MCT Notice Eff D/T: 08/19/2026 3:25 PM MCT Notice End D/T: Reqrd Rsp Desc: No response required Rsp D/T: Notice ID: 26-155 Prior Notice: 26-142 Subject: Burley Compressor Station Deficiency Period Notice Text: As indicated in All Shippers Notice #26-142, Northwest is 
currently performing maintenance at the Burley CS through gas 
day August 24, 2026. 

Primary northbound nomination requests at the Burley CS have 
exceeded the available capacity of 336,000 Dth/d northbound (or 
whatever Northwest cannot mitigate). Therefore, pursuant to 
Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's 
Tariff, Northwest hereby gives notice of a Deficiency Period 
for Gas Day August 20, 2026. The Deficiency will be calculated 
based on a design capacity of 579,000 Dth/d northbound. The 
Deficiency Period will continue until the work is completed. 
Northwest will post on its EBB if unable to mitigate volumes 
each day until the work is completed.

Please reference the Maintenance Schedule tab at 
www.northwest.williams.com for more information.


If you have any questions, please call your Commercial Services 
Representative or the hotline at 713-215-6301.