Northwest Pipeline LLC NOTICE #32478 Chehalis Compressor Station Deficiency Period posted on Oct 21 2025 3:28PM TSP Name: Northwest Pipeline LLC TSP: 67977322 Critical: Y Notice Stat Desc: SUPERSEDE Notice Type Desc: CURTAILMENT Post D/T: 10/21/2025 3:28 PM MCT Notice Eff D/T: 10/21/2025 3:28 PM MCT Notice End D/T: Reqrd Rsp Desc: No response required Rsp D/T: Notice ID: 25-192 Prior Notice: 25-190 Subject: Chehalis Compressor Station Deficiency Period Notice Text: As indicated in All Shippers Notice #25-190, Northwest is 
currently performing maintenance on Unit 1 and Unit 2 at the 
Chehalis compressor station through October 25, 2025. 

Primary southbound nomination requests at the Chehalis 
compressor have exceeded the available capacity of 490,000 
Dth/d southbound (or whatever Northwest cannot mitigate). 
Therefore, pursuant to Sections 10.2 and 10.3 of Rate Schedule 
TF-1 in Northwest's Tariff, Northwest hereby gives notice of a 
Deficiency Period for Gas Day October 22, 2025. The Deficiency 
will be calculated based on a design capacity of 672,000 Dth/d 
southbound. The Deficiency Period will continue until the work 
is completed. Northwest will post on its EBB if unable to 
mitigate volumes each day until the work is completed.

Please reference the Maintenance Schedule tab at 
www.northwest.williams.com for more information.


If you have any questions, please call your Commercial Services 
Representative or the hotline at 713-215-6301.