Northwest Pipeline LLC NOTICE #32300 Moab DOT Hydro Test Update posted on Jul 16 2025 9:02AM TSP Name: Northwest Pipeline LLC TSP: 67977322 Critical: Y Notice Stat Desc: SUPERSEDE Notice Type Desc: MAINTENANCE Post D/T: 07/16/2025 7:45 AM MCT Notice Eff D/T: 07/16/2025 7:45 AM MCT Notice End D/T: Reqrd Rsp Desc: No response required Rsp D/T: Notice ID: 25-100 Prior Notice: 25-097 Subject: Moab DOT Hydro Test Update Notice Text:
As referenced in All Shippers Notice #25-097, the Moab DOT
Hydrotest between Pleasant View CS and the La Plata B CS that
was scheduled to begin Gas Day July 15, 2025 through Gas Day
July 25, 2025 has been delayed due to unforeseen circumstances
after initial start of work. The schedule has been revised with
testing to restart on Gas Day July 22, 2025 through Gas Day
August 1, 2025.
In the interim, Northwest Pipeline will lift the Deficiency
Period (All Shippers Notice #25-099) and place the line back
in-service starting Gas Day July 17 through Gas Day July 21.
This ensures continued service, reliability and minimizes
disruption to its customers.
We appreciate your understanding and cooperation as we work to
complete this testing safely and efficiently.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please contact your Commercial
Services Representative or the hotline at 713-215-6301.