Northwest Pipeline LLC
NOTICE #31814
Pocatello Unit 1 Maintenance, Albany Engine Exchange, Soda Springs ESD, Baker to posted on Jul 18 2024 3:06PM
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 07/18/2024 3:04 PM MCT
Notice Eff D/T: 07/18/2024 3:04 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 24-112
Prior Notice:
Subject: Pocatello Unit 1 Maintenance, Albany Engine Exchange, Soda Springs ESD, Baker to
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest is performing the Pocatello Unit 1
Maintenance at the Pocatello CS beginning Gas Day July 22,
2024, through Gas Day July 26, 2024, the Albany Engine Exchange
at the Albany CS beginning Gas Day July 22, 2024, through Gas
Day July 26, 2024, the Soda Springs ESD at the Soda Springs CS
beginning Gas Day July 23, 2024, through July 24, 2024, the
Baker to Meacham SCCDA Digs #3 at the Meacham CS beginning Gas
Day July 24, 2024, through Gas Day September 06, 2024, and the
Boise Hydro Test #2 at the Boise CS beginning Gas Day July 25,
2024, through Gas Day August 03, 2024.
The cut point for the Pocatello Unit 1 Maintenance will be the
Pocatello CS which will be limited to 596,000 Dth/d northbound
for the duration of the outage.
If primary nomination requests through the Pocatello CS exceed
the available capacity of 596,000 Dth/d northbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 610,000 Dth/d
northbound. The deficiency period will continue until the work
is completed on Gas Day July 26, 2024.
The cut point for the Albany Engine Exchange will be the Albany
CS which will be limited to 116,000 Dth/d northbound for the
duration of the outage.
If primary nomination requests through the Albany CS exceed
the available capacity of 116,000 Dth/d northbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 120,000 Dth/d
northbound. The deficiency period will continue until the work
is completed on Gas Day July 26, 2024.
The cut point for the Soda Springs ESD will be the Soda Springs
CS which will be limited to 570,000 Dth/d northbound for the
duration of the outage.
If primary nomination requests through the Soda Springs CS
exceed the available capacity of 570,000 Dth/d northbound (or
whatever NWP cannot mitigate during any day of the
maintenance), pursuant to Sections 10.2 and 10.3 of Rate
Schedule TF-1 in Northwest's Tariff, Northwest will give notice
of a Declared Deficiency Period based on a design capacity of
652,000 Dth/d northbound. The deficiency period will continue
until the work is completed on Gas Day July 24, 2024.
The cut point for the Baker to Meacham SCCDA Digs will be the
Meacham CS which will be limited to 441,000 Dth/d southbound
for the duration of the outage.
If primary nomination requests through the Meacham CS exceed
the available capacity of 441,000 Dth/d Southbound (or whatever
NWP cannot mitigate during any day of the maintenance),
pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest will give notice of a Declared
Deficiency Period based on a design capacity of 500,000 Dth/d
southbound. The deficiency period will continue until the work
is completed on Gas Day September 06, 2024.
The cut point for the Boise Hydro Test #2 will be the Boise CS
which will be limited to 419,000 Dth/d northbound and 367,000
Dth/d southbound for the duration of the outage.
If primary nomination requests through the Boise CS exceed the
available capacity of 419,000 Dth/d northbound or 367,000 Dth/d
southbound (or whatever NWP cannot mitigate during any day of
the maintenance), pursuant to Sections 10.2 and 10.3 of Rate
Schedule TF-1 in Northwest's Tariff, Northwest will give notice
of a Declared Deficiency Period based on a design capacity of
499,000 Dth/d northbound or 452,000 Dth/d southbound. The
deficiency period will continue until the work is completed on
Gas Day August 03, 2024.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.