McMinnville CS Generator Replacement & Mt. Vernon CS ESD Test - Maintenance Remi posted on Jul 2 2024 1:28PM
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 07/02/2024 1:25 PM MCT
Notice Eff D/T: 07/02/2024 1:25 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 24-106
Prior Notice:
Subject: McMinnville CS Generator Replacement & Mt. Vernon CS ESD Test - Maintenance Remi
Notice Text:
As posted in the maintenance schedule on Northwest Pipeline's
website, Northwest is performing a generator replacement at the
McMinnville CS beginning Gas Day July 08, 2024, through Gas Day
July 23, 2024, and an ESD Test at the Mt. Vernon CS beginning
Gas Day July 09, 2024, through Gas Day July 10, 2024.
The cut point for the McMinnville Generator Replacement will be
the McMinnville CS which will be limited to 171,000 Dth/d
northbound for the duration of the outage.
The cut point for the Mt. Vernon ESD Test will be the Mt.
Vernon CS which will be limited to 1,240,000 Dth/d southbound
for the duration of the outage.
If primary nomination requests through the McMinnville CS
exceed the available capacity of 171,000 Dth/d northbound (or
whatever NWP cannot mitigate during any day of the
maintenance), pursuant to Sections 10.2 and 10.3 of Rate
Schedule TF-1 in Northwest's Tariff, Northwest will give notice
of a Declared Deficiency Period based on a design capacity of
206,000 Dth/d northbound. The deficiency period will continue
until the work is completed on Gas Day July 23, 2024.
If primary nomination requests through the Mt. Vernon CS exceed
the available capacity of 1,240,000 Dth/d southbound (or
whatever NWP cannot mitigate during any day of the
maintenance), pursuant to Sections 10.2 and 10.3 of Rate
Schedule TF-1 in Northwest's Tariff, Northwest will give notice
of a Declared Deficiency Period based on a design capacity of
1,277,000 Dth/d southbound. The deficiency period will continue
until the work is completed on Gas Day July 10, 2024.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial