TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: CURTAILMENT
Post D/T: 07/14/2022 2:49 PM MCT
Notice Eff D/T: 07/14/2022 2:49 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 22-105
Prior Notice: 22-088
Subject: Deficiency at Caldwell Compressor
Notice Text:
As posted in the maintenance schedule and as indicated in All Shippers Notice #22-088, Northwest is currently in Phase II of its pipe replacement project in the Caldwell to Boise corridor.
Primary nomination requests southbound through the Caldwell compressor have exceeded the available capacity of 372,000 Dth/d (or whatever Northwest can mitigate). Therefore, pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's Tariff, Northwest hereby gives notice of a Deficiency Period for gas day Friday, July 15, 2022. Based on a design capacity of 475,000 Dth/d southbound at Caldwell the Daily Deficiency Volume is 372,000 Dth/d. The Deficiency Period will continue until the work is completed August 5, 2022. Northwest will post on its EBB if unable to mitigate volumes each day throughout the Deficiency Period.
If you have any questions, please call your Commercial Services Representative or the hotline at 713-215-6301.
|