TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: MAINTENANCE
Post D/T: 10/10/2018 3:59 PM MCT
Notice Eff D/T: 10/10/2018 3:59 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 18-104
Prior Notice: 18-101
Subject: Roosevelt Maintenance Update
Notice Text:
As previously posted in All Shipper Notice 18-101, Northwest is performing a
controls upgrade at the Roosevelt compressor station May 1, through October
15, 2018. The posted design capacity northbound at the Roosevelt compressor
is 400,000 Dth/d during the outage.
In anticipation of the Jackson Prairie Storage facility returning to service
as early as tonight, Northwest will attempt to mitigate primary firm
nominations beginning Gas Day October 11 northbound through Roosevelt that exceed the operationally available capacity.
Northwest will evaluate its system operations daily and if Northwest is
unable to mitigate these excess volumes, Northwest will declare a deficiency
period pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff.
If you have any questions, please call your Marketing Services Representative
or the hotline at 713-215-6301.
NWP
DA/MR
|