Northwest Pipeline LLC NOTICE #30803 Spokane Mead to Ritzville Anomaly Investigations posted on Sep 13 2022 12:37PM TSP Name: Northwest Pipeline LLC TSP: 67977322 Critical: Y Notice Stat Desc: INITIATE Notice Type Desc: MAINTENANCE Post D/T: 09/13/2022 12:04 PM MCT Notice Eff D/T: 09/13/2022 12:04 PM MCT Notice End D/T: Reqrd Rsp Desc: No response required Rsp D/T: Notice ID: 22-143 Prior Notice: Subject: Spokane Mead to Ritzville Anomaly Investigations Notice Text:
Subject: Spokane Mead to Ritzville Immediate
Anomaly Investigations
As posted on its maintenance schedule, Northwest conducted in-line
inspections within the Spokane Meade to Ritzville corridor. Northwest
will be performing anomaly investigations in the Spokane Mead to Ritzville
corridor beginning immediately on September13, 2022, through gas day
October 7, 2022. In conjunction with the work, the Starr Road receipt point
capacity will be reduced from the design capacity of 165,000 Dth/d to
20,000 Dth/d during the work.
Northwest will mitigate the work to the highest extent possible. If Northwest
is unable to successfully mitigate all of the primary Nominations, it will
declare a deficiency period pursuant to Sections 10.2 and 10.3 of
Rate Schedule TF-1 in Northwest's Tariff based on the design capacity and
maintenance restriction stated above.
If you have any questions, please call your Commercial Services Representative
or the hotline at 713-215-6301.