Northwest Pipeline LLC NOTICE #30756 Spokane Pipe Replacement Update posted on Aug 3 2022 8:43AM TSP Name: Northwest Pipeline LLC TSP: 67977322 Critical: Y Notice Stat Desc: INITIATE Notice Type Desc: MAINTENANCE Post D/T: 08/03/2022 8:42 AM MCT Notice Eff D/T: 08/03/2022 8:42 AM MCT Notice End D/T: Reqrd Rsp Desc: No response required Rsp D/T: Notice ID: 22-115 Prior Notice: Subject: Spokane Pipe Replacement Update Notice Text:

As part of Northwest’s scheduled maintenance and as indicated

in All Shippers Notice #22-091, Northwest is currently

replacing pipe along the Spokane lateral.

 

Effective for gas day August 4, 2022, Northwest will be limiting

capacity at Mesa compressor to 0 Dth/d in the northbound and southbound

direction. If primary nomination requests through the Mesa compressor

exceed the available capacity of 0 Dth/d (or whatever Northwest can mitigate)

in the northbound or southbound direction, Northwest will give notice of a

Deficiency Period, pursuant to sections 10.2 and 10.3 of Rate Schedule TF-1 in

Northwest's Tariff.

 

The Deficiency will be calculated based on the design capacity of 143,896 Dth/d

northbound or 75,338 Dth/d southbound at the Mesa compressor. The Deficiency

Period will continue through gas day August 11 or whenever the work is completed

and Northwest will post on its EBB if unable to mitigate volumes on that day.

 

If you have any questions, please call your Commercial Services

Representative or the hotline at 713-215-6301.