Northwest Pipeline LLC
NOTICE #30707
Deficiency at Mesa Compressor posted on Jul 11 2022 3:32PM
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: INITIATE
Notice Type Desc: CURTAILMENT
Post D/T: 07/11/2022 3:10 PM MCT
Notice Eff D/T: 07/11/2022 3:10 PM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 22-093
Prior Notice:
Subject: Deficiency at Mesa Compressor
Notice Text:
As part of Northwest’s scheduled maintenance and as indicated
in All Shippers Notice #22-091, Northwest is currently
replacing pipe along the Spokane lateral.
Primary nomination requests southbound through the Mesa
compressor have exceeded the available capacity of 0 Dth/d (or
whatever Northwest can mitigate). Therefore, pursuant to
sections 10.2 and 10.3 of Rate Schedule TF-1 in Northwest's
Tariff, Northwest hereby gives notice of a Deficiency Period
for gas day Tuesday, July 12, 2022. Deficiency will be
calculated based on the design capacity of 75,338 Dth/d
southbound at the Mesa compressor. The Deficiency Period will
continue through gas day July 13 and Northwest will post on its
EBB if unable to mitigate volumes on that day.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.