Northwest Pipeline LLC NOTICE #30693 Revised - Willard Deficiency Period Update posted on Jul 2 2022 4:20PM TSP Name: Northwest Pipeline LLC TSP: 67977322 Critical: Y Notice Stat Desc: SUPERSEDE Notice Type Desc: CURTAILMENT Post D/T: 07/02/2022 4:09 PM MCT Notice Eff D/T: 07/02/2022 4:09 PM MCT Notice End D/T: Reqrd Rsp Desc: No response required Rsp D/T: Notice ID: 22-085 Prior Notice: 22-084 Subject: Revised - Willard Deficiency Period Update Notice Text:
The Willard compressor deficiency period, as declared in All
Shipper Notice 22-077, is expected to be completed by the end
of gas day July 3, 2022. However, Northwest will be accepting
nominations at the Willard compressor station up to the design
capacity of 407,000 Dth/d southbound immediately.
As a reminder, the second hydrotest in between the Willard and
Goldendale compressor corridor will begin on July 5, 2022, and
is expected to last through July 14, 2022.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
NWP