Northwest Pipeline LLC NOTICE #29194 Declared Deficiency Period at Rangley Compressor - Revised posted on Oct 7 2019 9:02AM TSP Name: Northwest Pipeline LLC TSP: 67977322 Critical: Y Notice Stat Desc: SUPERSEDE Notice Type Desc: CURTAILMENT Post D/T: 10/07/2019 9:02 AM MCT Notice Eff D/T: 10/07/2019 9:02 AM MCT Notice End D/T: Reqrd Rsp Desc: No response required Rsp D/T: Notice ID: 19-165 Prior Notice: 19-164 Subject: Declared Deficiency Period at Rangley Compressor - Revised Notice Text:
The following notice was posted on Sunday October 6, 2019 as a non-critical
notice. It is being reposted as a critical notice.
As posted in the maintenance schedule on Northwest's website, Northwest is
performing valve replacement work at the Rangely compressor station October
7, 2019 through October 12, 2019.
Primary nomination requests through the Rangely compressor have exceeded the
available capacity of 263,000 Dth/d which Northwest can’t mitigate.
Therefore, pursuant to Sections 10.2 and 10.3 of Rate Schedule TF-1 in
Northwest's Tariff, Northwest hereby gives notice of a Declared Deficiency
Period beginning gas day Monday October 7, 2019. Based on a design capacity
of 350,655 Dth/d, the Daily Deficiency Volume is 87,655 Dth/d. The deficiency
period will continue through October 12,2019.
If you have any questions, please call your Marketing Services Representative
or the hotline at 801/584-7301.